BOILER PRESSURE PART WORK:
DE has well design engineers with all facilities. DE is one of the most trusted name in boiler up-gradation.
We increase capacity of steam generation of boiler with increasing furnace capacity, heating surface, suitable economizer size and all equipment regarding to this process.
The main goal of DE for up-gradation of boiler is increase steam generation with increasing efficiency.
DE UPGRADED PROJECTS :
Sr No. | Customer Name | Capacity | Nos |
---|---|---|---|
01 | Sant Muktai Sugar & Energy Ltd | 32TPH To 38TPH | 02 |
02 | Om Sugars Ltd | 35TPH To 38TPH | 02 |
03 | Laila Sugars Pvt Ltd | 32TPH To 38TPH | 01 |
04 | Bageshwari Sugar Ltd | 32TPH To 38TPH | 02 |
05 | Sahyadri Starch & Industries Pvt Ltd | 32TPH To 38TPH | 01 |
06 | Baliraja Sakhar Karkhana Ltd | 08TPH To 14TPH | 01 |
DE have well erection facilities. We have separate erection Department for handling all work regarding erection of boiler with separate team and workers. We have all equipments required for erection work of boiler such as Crain/hydra, winch machines, small manual handling 3phase/1phase welding machines, transportation facilities and some other facilities require for erection work.
DE is very punctual for it1s time management. We done our job in time which is given by customer.DE done its job with good quality and safety.
DE UPGRADED PROJECTS :
Sr No. | Customer Name | Capacity | Nos |
---|---|---|---|
01 | Om Sugars Ltd | 21TPH | 02 |
02 | Om Sugars Ltd | 38TPH | 01 |
03 | Victoria Agro | 40TPH | 01 |
04 | Sharad S S K Ltd | 20TPH | 01 |
05 | Lakshimi Organic Ltd | 30TPH | 01 |
06 | Ankaleshwar | 10TPH | 01 |